[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-779585":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},779585,500,1,"单选题","甲公司的某产品需要经过两道工序加工完成，第一道工序用时30小时，在产品数量为200件，第二道工序用时20小时，在产品数量为400件，假定各工序内在产品完工程度平均为50%。第二道工序在产品约当产量为（ ）件。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","80",false,{"key":16,"text":17,"correct":14},"B","120",{"key":19,"text":20,"correct":14},"C","200",{"key":22,"text":23,"correct":24},"D","320",true,"第二道工序的完工程度=（30＋20×50%）\u002F（30+20）=80%，第二道工序的约当产量=400×80%=320（件）。",{"id":6,"name":27,"category":28,"favorite":29},"财务与会计","会计财税",0]