[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-779476":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},779476,500,2,"多选题","(2016年)对于同一投资项目而言，下列关于固定资产投资决策方法的表述中，错误的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","净现值、现值指数和内含报酬率的评价结果一致",false,{"key":16,"text":17,"correct":18},"B","如果净现值大于零，其投资回收期一定短于项目经营期的1\u002F2",true,{"key":20,"text":21,"correct":14},"C","如果净现值大于零，其内含报酬率一定大于设定的折现率",{"key":23,"text":24,"correct":18},"D","投资回收期和投资回报率的评价结果一致",{"key":26,"text":27,"correct":14},"E","如果净现值大于零，其现值指数一定大于1","BD","投资回收期和投资回报率都属于非折现指标，没有考虑时间价值，两个指标的评价结果不一定一致，同时它们的大小和考虑时间价值的净现值大小之间没有对应关系，所以选择选项B、D。",{"id":6,"name":31,"category":32,"favorite":33},"财务与会计","会计财税",0]