[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-775449":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},775449,498,2,"多选题","投资项目初始现金流量的组成部分主要有（ ）。[2008年中级真题]",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","固定资产投资",true,{"key":16,"text":17,"correct":14},"B","流动资产投资",{"key":19,"text":20,"correct":14},"C","其他投资费用",{"key":22,"text":23,"correct":24},"D","借款资本化利息",false,{"key":26,"text":27,"correct":14},"E","原有设备变价收入","ABCE","初始现金流量是指开始投资时发生的现金流量，通常包括如下几个部分：①固定资产上的投资，包括固定资产购入或建造成本、运输成本和安装成本等；②营运资金垫支，是指投资项目建成后，必须垫支一定的营运资本才能入运营，这部分垫支的营运资本一般要到项目寿命终结时才能收回；③其他投资费用，包括与投资项目有关的培训费、注册费等费用；④原有固定资产的变价收入，这部分现金流入是对前面三部分现金流出的抵减，减少了项目的投资源。D项，借款资本化利息属于在投资项目建设过程中随项目的建设不断流出，不是初始现金流。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 审计专业相关知识","会计财税",0]