[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-775447":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},775447,498,2,"多选题","评价项目投资具备财务可行性的重要标准有（ ）。[2008年初级真题]",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","项目的净现值大于或等于0",true,{"key":16,"text":17,"correct":18},"B","项目的预期收益率大于或等于0",false,{"key":20,"text":21,"correct":18},"C","项目的投资回收期年限小于或等于1",{"key":23,"text":24,"correct":14},"D","项目的内部报酬率大于或等于必要报酬率",{"key":26,"text":27,"correct":18},"E","项目的必要报酬率大于或等于预期收益率","AD","BE两项，当项目的预期收益率超过项目的必要报酬率（项目的资本成本）时，项目可取。C项，单一方案或非互斥方案决策时，应该事先制订一个投资回收期的目标用于比较，短于目标投资回收期的方案可行；互斥方案比较时，超过目标投资回收期的方案中，回收年限越短的方案越好。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 审计专业相关知识","会计财税",0]