[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-772680":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},772680,497,2,"多选题","下列各项中，不属于审计项目计划文字部分的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","本年度审计项目安排的依据和指导思想",false,{"key":16,"text":17,"correct":18},"B","完成审计项目的时间要求和责任单位",true,{"key":20,"text":21,"correct":18},"C","被审计单位名称以及主管部门和所在地区",{"key":23,"text":24,"correct":14},"D","上年度审计计划完成情况",{"key":26,"text":27,"correct":14},"E","完成计划的主要措施","BC","审计项目计划由文字和表格两部分组成。文字部分的内容包括：①上年度审计项目计划完成情况；②本年度审计项目安排的依据和指导思想；③审计目的；④完成计划的主要措施。表格部分的内容包括：①审计项目名称、类别、级别和数量；②完成审计项目的时间要求和责任单位；③被审计单位名称及其主管部门和所在地区。BC两项属于表格部分。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 审计理论与实务","会计财税",0]