[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-772655":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},772655,497,1,"单选题","根据国家审计准则的规定，对审计项目实施结果承担最终责任的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","审计组组长",false,{"key":16,"text":17,"correct":14},"B","审计机构",{"key":19,"text":20,"correct":21},"C","审计机关负责人",true,{"key":23,"text":24,"correct":14},"D","总审计师","审计机关负责人的工作职责包括：①审定审计项目目标、范围和审计资源的配置；②指导和监督检查审计工作；③审定审计文书和审计信息；④审计管理中的其他重要事项。审计机关负责人对审计项目实施结果承担最终责任。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 审计理论与实务","会计财税",0]