[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-772152":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},772152,497,1,"单选题","下列各项中，不属于绩效审计准备阶段工作内容的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","确定审计目标和评价标准",false,{"key":16,"text":17,"correct":14},"B","设计审计方法体系",{"key":19,"text":20,"correct":14},"C","编制审计方案",{"key":22,"text":23,"correct":24},"D","归纳审计证据形成审计结论",true,"就单个绩效审计项目而言，审计准备阶段需要做的主要工作有：初步调查了解审计事项；确定审计目标和范围、重点；确定审计评价标准；设计审计方法体系；编制审计方案。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 审计理论与实务","会计财税",0]