[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-771574":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},771574,496,1,"单选题","某公司资本成本10%，该公司考虑资本成本后决定投资A项目，据此可推断（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","用10%折现率计算A项目的净现值大于0",true,{"key":16,"text":17,"correct":18},"B","A项目会计上披露的报酬率大于10%",false,{"key":20,"text":21,"correct":18},"C","A项目的内含报酬率小于10%",{"key":23,"text":24,"correct":18},"D","用10%折现率计算A项目的净现值小于0","公司使用净现值法评估投资项目时，可使用资本成本作为折现率，净现值大于0，表示可以投资。",{"id":6,"name":27,"category":28,"favorite":29},"国际注册内部审计师","会计财税",0]