[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-771104":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},771104,496,1,"单选题","某车间对项目的管理采用关键路径法，其生产工序及所需时间如下图，字母表示工序，数字表示工序所需时间，单位是小时，则完成全部工序所需的最短时间是：",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","６小时",false,{"key":16,"text":17,"correct":18},"B","７小时",true,{"key":20,"text":21,"correct":14},"C","８小时",{"key":23,"text":24,"correct":14},"D","９小时","根据箭头表示，生成C需要B和A分别完成，生成D需要E和C分别完成，生成Ｆ需要Ｅ和Ｄ分别都完成，所以生成C需要的最短时间是1+3=4小时，而从A-B-E-F需要1+2+3=6小时，从A-C-D-F需要1+3+2+1=7小时，所以完成全部工序所需的最短时间是7小时。",{"id":6,"name":27,"category":28,"favorite":29},"国际注册内部审计师","会计财税",0]