[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-771103":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},771103,496,1,"单选题","某车间对项目的管理采用关键路径法，其生产工序及所需时间如下图，字母表示工序，数字表示工序所需时间，单位是小时，不能有任何延误的是：",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","A-B工序",true,{"key":16,"text":17,"correct":18},"B","A-C工序",false,{"key":20,"text":21,"correct":18},"C","B-E工序",{"key":23,"text":24,"correct":18},"D","E-F工序","A-B工序是关键路径，不能有任何延误，否则将延长整个工序的时间。",{"id":6,"name":27,"category":28,"favorite":29},"国际注册内部审计师","会计财税",0]