[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-771102":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},771102,496,1,"单选题","在项目进度管理中，利用概率计算活动周期的项目管理方法是：",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","关键路径法",false,{"key":16,"text":17,"correct":14},"B","甘特图法",{"key":19,"text":20,"correct":21},"C","项目计划评审技术",true,{"key":23,"text":24,"correct":14},"D","六西格玛法","关键路径法与项目计划评审技术都是项目管理方法，区别就在于前者假定活动的周期固定，后者使用概率周期；甘特图是比较简单的项目进度管理方法，使用坐标轴表示在整个期间上计划的和实际的活动完成情况；六西格玛法是质量管理方法。",{"id":6,"name":27,"category":28,"favorite":29},"国际注册内部审计师","会计财税",0]