[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-771095":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},771095,496,1,"单选题","以下信息适用于甲公司的A项目，则A项目的最短完成时间是：",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","7小时",false,{"key":16,"text":17,"correct":14},"B","8小时",{"key":19,"text":20,"correct":21},"C","11小时",true,{"key":23,"text":24,"correct":14},"D","22小时","F是最终环节，而F需C,D,E全部完成才可以执行F。完成C的时间是2+5=7小时，完成D的时间是3+4=7小时，完成E的时间是3+5=8小时，所以C,D,E全部完成的最短时间是8小时，F本身的作业时间是3小时，因此完成F所需的最短时间是8+3=11小时。",{"id":6,"name":27,"category":28,"favorite":29},"国际注册内部审计师","会计财税",0]