[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-770658":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},770658,496,1,"单选题","某首席审计执行官在审计工作中考虑审计项目的控制和预算的审计时间，那么该首席审计执行官认为，在何时做出修订时间预算的决定是合理的：",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","在发现某些需要进一步测试的审计发现时",false,{"key":16,"text":17,"correct":14},"B","当发现现有的时间确实不能完成审计活动时",{"key":19,"text":20,"correct":14},"C","当审计工作小组的人员发生大的变动时",{"key":22,"text":23,"correct":24},"D","在初步调查业务完成时",true,"应该在初步调查业务，编制审计方案后，应该对时间预算进行评估，以确定预算的时间是否合理、是否需要修订。",{"id":6,"name":27,"category":28,"favorite":29},"国际注册内部审计师","会计财税",0]