[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-770005":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},770005,496,1,"单选题","在确定施工延误索赔的有效性时，以下哪项风险最大？",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","在完工之前就递交了承包商索赔。",false,{"key":16,"text":17,"correct":18},"B","承包商的索赔包括工程固定价格部分的费用。",true,{"key":20,"text":21,"correct":14},"C","承包商的索赔包括转包商对转包造成的差额估值。",{"key":23,"text":24,"correct":14},"D","承包商索赔过低。","A不正确。在工程竣工之前如果已经造成延误而提交其延误索赔要求也应该是合适的。B正确。承包商的延误索赔要求如果包括已在工程固定价格部分得到考虑的成本，如果这样的话成本会无限扩大，比如某一项固定费用在原来的承包价内已经包含而且并没有因为延误造成损失就不应该重复计算，所以B是最大的风险。C不正确。分包商对于其应得工程余额的估算可以用于计算潜在的损失。D不正确。低报索赔金额仍然属于索赔金额范围内是可行的。",{"id":6,"name":27,"category":28,"favorite":29},"国际注册内部审计师","会计财税",0]