[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-769679":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},769679,496,1,"单选题","某公司计划建造一座新办公楼，与一承包商签订了3000万美元固定价格的承包合同。以下哪项内容带来的风险最大？",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","材料以次充好。",false,{"key":16,"text":17,"correct":14},"B","人工费用超支。",{"key":19,"text":20,"correct":21},"C","工程不能及时完工。",true,{"key":23,"text":24,"correct":14},"D","对材料、设备等实物保管不善。","在审计固定价格合同时，《索耶内部审计》要求内部审计师检查下列风险因素：●不充分的竞争；●不充分的保险和合同覆盖面；●在工程实际完工前就认定工程已完成；●为没有收到的设备或没有完成的活动支付费用；●加价条款（针对特殊情况，如因物价上涨而增加费用的条款）；●对增加权利和修改权利的授权；●单独支付的经费支出；●变更订单；●没有对照条款进行充分检查。",{"id":6,"name":27,"category":28,"favorite":29},"国际注册内部审计师","会计财税",0]