[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-768184":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},768184,496,1,"单选题","某组织一个建设项目的成本最近严重超支，管理层怀疑这些成本超支因承包商对合约变更订单进行不当收费而产生。以下哪些程序适用来检测这种猜疑是否正确？？Ⅰ．确认承包商更改订单是否得到管理层适当核准；Ⅱ．确认承包商是否针对被变更订单取消的原承包工程开账单；Ⅲ．确认承包商是否针对变更订单再次收取原合约已支付的费用；Ⅳ．确认是否就尚未完成的变更订单向承包商作出支付。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","Ⅰ和Ⅱ。",false,{"key":16,"text":17,"correct":14},"B","Ⅰ和Ⅲ。",{"key":19,"text":20,"correct":21},"C","Ⅱ和Ⅲ。",true,{"key":23,"text":24,"correct":14},"D","Ⅲ和Ⅳ。","Ⅰ．不正确。这一程序测试的是公司是否已同意承包商变更定货合同，但没有测试是否承包商正确地核算了与变更定货合同相关的成本。Ⅱ．正确。该程序关注的是定货合同变更后成本计算的准确性。Ⅲ．正确。该程序关注的是定货合同变更后成本的恰当性。Ⅳ．不正确。这一程序涉及支付程序，与成本超支无关。",{"id":6,"name":27,"category":28,"favorite":29},"国际注册内部审计师","会计财税",0]