[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-766035":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},766035,495,1,"单选题","在对某独立投资项目进行财务评价时，下列各项中，不能据以判断该项目具有财务可行性的是：",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","内部报酬率大于必要报酬率",false,{"key":16,"text":17,"correct":18},"B","投资回收期小于项目寿命期",true,{"key":20,"text":21,"correct":14},"C","以必要报酬率作为折现率计算的项目净现值大于0",{"key":23,"text":24,"correct":14},"D","预期投资利润率高于目标投资利润率","投资回收期短于目标投资回收期，表明投资项目具有财务可行性。",{"id":6,"name":27,"category":28,"favorite":29},"(初级) 审计专业相关知识","会计财税",0]