[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-765981":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},765981,495,2,"多选题","下列各项预算中，以生产预算为编制基础的有：",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","销售预算",false,{"key":16,"text":17,"correct":18},"B","直接材料预算",true,{"key":20,"text":21,"correct":18},"C","直接人工预算",{"key":23,"text":24,"correct":14},"D","固定制造费用预算",{"key":26,"text":27,"correct":18},"E","变动制造费用预算","BCE","生产预算是在销售预算的基础上编制的；直接材料预算、直接人工预算、变动制造费用预算都以生产预算为基础编制；固定制造费用预算需要逐项进行预计，通常与本期产量无关。",{"id":6,"name":31,"category":32,"favorite":33},"(初级) 审计专业相关知识","会计财税",0]