[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-759270":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},759270,489,1,"单选题","现有两个投资项目甲和乙，已知甲、乙方案的期望值分别为20%、28%，标准差分别为30%、55%，那么()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","甲项目的风险程度大于乙项目的风险程度",false,{"key":16,"text":17,"correct":18},"B","甲项目的风险程度小于乙项目的风险程度",true,{"key":20,"text":21,"correct":14},"C","甲项目的风险程度等于乙项目的风险程度",{"key":23,"text":24,"correct":14},"D","两个项目的风险程度不能确定","标准差仅适用于预期值相同的情况，在预期值相同的情况下，标准差越大，风险越大；变异系数适用于预期值相同或不同的情况，在预期值不同的情况下，变异系数越大，风险越大。两个投资项目的期望值不同，所以应用变异系数比较。甲项目的变异系数=30c%\u002F20%=1.5，乙项目的变异系数=55%\u002F28%=1.96，故甲项目的风险程度小于乙项目。",{"id":6,"name":27,"category":28,"favorite":29},"理财规划师（三级）","会计财税",0]