[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-752988":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},752988,486,2,"多选题","甲公司以出包方式建造厂房。建造过程中发生的下列支出中，应计入所建造固定资产成本的有（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","支付给第三方监理公司的监理费",true,{"key":16,"text":17,"correct":14},"B","季节性因素暂停建造期间外币专门借款汇兑损益",{"key":19,"text":20,"correct":21},"C","为取得土地使用权而缴纳的土地出让金",false,{"key":23,"text":24,"correct":14},"D","建造期间进行试生产发生的负荷联合试车费用","ABD","选项A，支付给第三方监理公司的监理费属于待摊支出，因此计入所建造固定资产成本；选项B，季节性因素属于正常原因，因此暂停建造期间应该继续资本化；选项C，为取得土地使用权而缴纳的土地出让金应当确认为无形资产。",{"id":6,"name":28,"category":29,"favorite":30},"中级会计实务","会计财税",1]