[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-748120":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},748120,484,1,"单选题","若某投资项目的投资期为零，则直接利用年金现值系数计算该项目内含报酬率指标所要求的前提条件是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","投产后现金净流量为普通年金形式",true,{"key":16,"text":17,"correct":18},"B","投产后现金净流量为递延年金形式",false,{"key":20,"text":21,"correct":18},"C","投产后各年的现金净流量不相等",{"key":23,"text":24,"correct":18},"D","在建设起点没有发生任何投资","在全部投资均于建设起点一次投入，投资期为零，投产后每年现金净流量相等的情况下，则可直接利用年金现值系数计算该项目的内含报酬率指标，此时的年金现值系数正好等于该方案的静态回收期。",{"id":6,"name":27,"category":28,"favorite":7},"中级会计-财务管理","会计财税"]