[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-748055":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},748055,484,2,"多选题","下列各项中，构成项目终结期的现金流量的有（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设备运输安装费",false,{"key":16,"text":17,"correct":18},"B","固定资产变价净收入",true,{"key":20,"text":21,"correct":18},"C","垫支营运资金的收回",{"key":23,"text":24,"correct":14},"D","原材料购置费","BC","终结阶段的现金流量主要是现金流入量，包括固定资产变价净收入、固定资产变现净损益和垫支营运资金的收回。",{"id":6,"name":28,"category":29,"favorite":30},"中级会计-财务管理","会计财税",1]