[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-748029":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},748029,484,1,"单选题","（2018年）在对某独立投资项目进行财务评价时，下列各项中，并不能据以判断该项目具有财务可行性的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","以必要收益率作为折现率计算的项目，现值指数大于1",false,{"key":16,"text":17,"correct":14},"B","以必要收益率作为折现率计算的项目，净现值大于0",{"key":19,"text":20,"correct":21},"C","项目静态投资回收期小于项目寿命期",true,{"key":23,"text":24,"correct":14},"D","以必要收益率作为折现率，计算的年金净流量大于0","在评价单一方案时，当净现值大于0时，现值指数大于1，年金净流量大于0，内含收益率大于要求的收益率，项目具有财务可行性，所以选项A、B、D正确。静态投资回收期是辅助评价指标，需要跟设定的期限进行比较来判断项目是否可行，而不是跟项目寿命期进行比较，选项C错误",{"id":6,"name":27,"category":28,"favorite":7},"中级会计-财务管理","会计财税"]