[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-747609":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},747609,484,1,"单选题","（2018年）下列预算中，在编制时不需要以生产预算为基础的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","变动制造费用预算",false,{"key":16,"text":17,"correct":18},"B","销售费用预算",true,{"key":20,"text":21,"correct":14},"C","产品成本预算",{"key":23,"text":24,"correct":14},"D","直接人工预算","销售费用预算应与销售预算相配合，不是以生产预算为基础的。",{"id":6,"name":27,"category":28,"favorite":7},"中级会计-财务管理","会计财税"]