[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-746163":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},746163,482,1,"单选题","（2015年）已知第一道工序定额工时为60小时，第二道工序定额工时为40小时，两道工序平均完成50%，则第一道工序完工率（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","60%",false,{"key":16,"text":17,"correct":14},"B","50%",{"key":19,"text":20,"correct":14},"C","40%",{"key":22,"text":23,"correct":24},"D","30%",true,"第一道工序的完工率=60×50%\u002F（60＋40）×100%=30% 第二道工序的完工率=（60＋40×50%）\u002F（60＋40）×100%=80%",{"id":6,"name":27,"category":28,"favorite":29},"初级会计实务","会计财税",0]