[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-848631":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":22},848631,465,1,"单选题","风管系统安装完毕,必须进行严密性检验,严密性检验应()。",[11,15,18],{"key":12,"text":13,"correct":14},"A","以分部为主",false,{"key":16,"text":17,"correct":14},"B","全部工程",{"key":19,"text":20,"correct":21},"C","以主干管为主",true,"风管系统安装后，必须进行严密性检验，合格后方能交付下道工序。风管系统严密性检验以主、干管为主。在加工工艺得到保证的前提下，低压风管系统可采用漏光法检测。",{"id":6,"name":24,"category":25,"favorite":26},"制冷与空调设备安装修理","特种作业",0]