[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-816228":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":22},816228,451,1,"单选题","系统吹扫时,所有()均应打开进行吹扫,并应在系统综合气密试验中再次吹扫。",[11,15,19],{"key":12,"text":13,"correct":14},"A","仪表引压管线",true,{"key":16,"text":17,"correct":18},"B","泵过滤器的盖",false,{"key":20,"text":21,"correct":18},"C","倒淋阀","",{"id":6,"name":24,"category":25,"favorite":26},"聚合工艺","特种作业",0]