[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-794336":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":22},794336,446,1,"单选题","某施工工地电气检修工作中,曾多次发生过违章送电,导致检修人员伤亡的恶性事故。为了防止异常送电造成事故,可采取综合的技术措施和组织措施。下列有关送电的做法中,错误的是()。",[11,15,19],{"key":12,"text":13,"correct":14},"A","严格按照计划工作时间送电",true,{"key":16,"text":17,"correct":18},"B","严格执行工作票制度和监护制度",false,{"key":20,"text":21,"correct":18},"C","在被检修装置外侧装临时接地线","",{"id":6,"name":24,"category":25,"favorite":26},"过氧化工艺","特种作业",0]