[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-754766":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":22},754766,432,1,"单选题","每一期筑坝充填作业之前,必须进行()。",[11,15,19],{"key":12,"text":13,"correct":14},"A","岸坡处理",true,{"key":16,"text":17,"correct":18},"B","坝坡稳定",false,{"key":20,"text":21,"correct":18},"C","操作维护","",{"id":6,"name":24,"category":25,"favorite":26},"尾矿作业","特种作业",0]