[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-726608":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":22},726608,411,1,"单选题","尾矿筑坝安全管理要求,每期堆坝作业之前,应严格按照()的坝面坡度,结合本期子坝高度放出子坝坝基的轮廓线;筑成的子坝应轮廓清楚,坡面平整,坝顶标高要一致。",[11,15,18],{"key":12,"text":13,"correct":14},"A","管理者要求",false,{"key":16,"text":17,"correct":14},"B","标准",{"key":19,"text":20,"correct":21},"C","设计",true,"",{"id":6,"name":24,"category":25,"favorite":26},"安全检查作业（地下矿山）","特种作业",0]