[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-722115":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},722115,401,3,"判断题","高处作业施工中,需要临时拆除或变动安全设施的,应经技术负责人审批签字,并组织有关部门验收,经验收合格后,方可实施。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"需要临时拆除或变动安全设施的 应经作业负责人审批签字。",{"id":6,"name":21,"category":22,"favorite":23},"高处安装、维护、拆除","特种作业",1]