[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-721855":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},721855,401,3,"判断题","拆除工程安全专项方案应经技术负责人或监理工程师签字批准后实施,一经批准不得变更。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"拆除工程开工前，应根据工程特点、构造情况、工程量等编制施工组织设计或安全专项施工方案，应经技术负责人和总监理工程师签字批准后实施。施工过程中如需变更，应经原审批准方可实施。",{"id":6,"name":21,"category":22,"favorite":23},"高处安装、维护、拆除","特种作业",1]