[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-721769":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},721769,401,3,"判断题","建筑施工图可以自行修改设计。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"施工图设计变更及修改流程 1.施工单位提出问题要求设计修改如设计图纸出入或错误,现场存在施工难度等 2.监理单位对施工单位的意见进行审核,确认 3.工程部对监理单位和施工单位的意见进行审核、确认 4.设计院设计小组或设计师设计 5.设计院设计好之后与工程部确认是否需要修改及意见，如果有，再与相关设计院沟通 6.设计院设计单位确认、留存或另行变更通知 7.变更修改通知单给工程部 8.再由监理单位领会变更内容、将通知单发到施工单位 9.施工单位接到变更通知单再从新进行施工。",{"id":6,"name":21,"category":22,"favorite":23},"高处安装、维护、拆除","特种作业",1]