[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-721359":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":22},721359,401,1,"单选题","20吨门式起重机,横梁和立柱的结构成“门”字型。工人在拆卸起重机过程的正确排序()。1、先将设备的四个立柱用绳索拉紧,借助其它起重设备吊住横梁,以保持起重机机构的平衡;2、先拆卸起重机横梁上的驾驶楼及其他附件,再松开横梁与立柱之间的连结螺栓(其他起重设备吊住横梁),待螺栓全部松开后再将螺栓全部拆卸下来.3、再利用其他起重设备平稳吊下横梁,并拆卸立柱。",[11,15,19],{"key":12,"text":13,"correct":14},"A","1-2-3",true,{"key":16,"text":17,"correct":18},"B","2-1-3",false,{"key":20,"text":21,"correct":18},"C","1-3-2","",{"id":6,"name":24,"category":25,"favorite":7},"高处安装、维护、拆除","特种作业"]