[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-721302":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":22},721302,401,1,"单选题","广告设施结构拆除的先后顺序是()。",[11,15,18],{"key":12,"text":13,"correct":14},"A","不管是否承重结构一律从上至下拆除",false,{"key":16,"text":17,"correct":14},"B","先拆除承重结构、后拆除非承重结构",{"key":19,"text":20,"correct":21},"C","先拆除非承重结构、后拆除承重结构",true,"广告设施结构拆除的先后顺序是先拆除非承重结构、后拆除承重结构。",{"id":6,"name":24,"category":25,"favorite":7},"高处安装、维护、拆除","特种作业"]