[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-721277":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":22},721277,401,1,"单选题","设备离安装地点较远的情况下,在运输过程中,一是检查路面是否平整;二是要准备枕木、滚杠、倒链(检查倒链的零部件是否灵敏有效,有问题不得使用),倒链的吨位必须大于设备的吨位()t以上,严禁使用小吨位的倒链。",[11,15,19],{"key":12,"text":13,"correct":14},"A","0.5",true,{"key":16,"text":17,"correct":18},"B","0.1",false,{"key":20,"text":21,"correct":18},"C","1.0","设备离安装地点较远的情况下，在运输过程中一定要注意安全，一是检查路面是否平整，二是要准备枕木、滚杠、倒链（检查倒链的零部件是否灵敏有效，有问题不得使用），倒链的吨位必须大于设备的吨位0.5吨以上，严禁使用小吨位的倒链。在运输过程中设备的前方及两边严禁有人，应平稳拉动。到安装地后应把滚杠、倒链取下，设备应牢固，方能进行安装。",{"id":6,"name":24,"category":25,"favorite":7},"高处安装、维护、拆除","特种作业"]