[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-721220":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":22},721220,401,1,"单选题","建设单位应当在拆除工程施工()前,按照要求将有关资料报送工程所在地有关部门备案。",[11,15,18],{"key":12,"text":13,"correct":14},"A","21日",false,{"key":16,"text":17,"correct":14},"B","7日",{"key":19,"text":20,"correct":21},"C","15日",true,"建设单位应当在拆除工程施工15日前，将下列资料报送建设工程所在地县级以上人民政府建设行政主管部门或者其他有关部门备案：（1）施工单位资质登记证明；（2）拟拆除建筑物、构筑物及可能危及毗邻建筑物的说明；（3）拆除施工组织设计；（4）堆放、清除废弃物的措施。",{"id":6,"name":24,"category":25,"favorite":7},"高处安装、维护、拆除","特种作业"]