[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-721206":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":22},721206,401,1,"单选题","热水立管除应满足一般立管安装需要外,一般情况下立管与干管连接采用()个弯头。",[11,15,19],{"key":12,"text":13,"correct":14},"A","2",true,{"key":16,"text":17,"correct":18},"B","1",false,{"key":20,"text":21,"correct":18},"C","3","热水立管：按设计要求加好套管。立管与导管连接要采用2个弯头。立管长度 达15m时要采用3个弯头。立管如有伸缩器安装同干管。首层立管距地面50cm应加闸阀。",{"id":6,"name":24,"category":25,"favorite":7},"高处安装、维护、拆除","特种作业"]