[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-721137":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":22},721137,401,1,"单选题","上杆塔作业前,应先检查根部、基础和()是否牢固。",[11,15,18],{"key":12,"text":13,"correct":14},"A","杆身",false,{"key":16,"text":17,"correct":14},"B","脚钉",{"key":19,"text":20,"correct":21},"C","拉线",true,"上杆塔作业前,应先检查杆塔根部、基础和拉 线是否牢固。新立杆塔在杆基未完全牢固或做好临时拉线前，严禁攀登。遇有冲刷、起土、上拔或导地线、拉线松动的杆塔，应先培土加固，打好临时拉线或支好杆架后，再行登杆。",{"id":6,"name":24,"category":25,"favorite":7},"高处安装、维护、拆除","特种作业"]