[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-720958":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":22},720958,401,1,"单选题","建筑物拆除时,应从上至下,逐层分段进行;应先拆除非承重结构,再拆除承重结构。属于()拆除施工方法。",[11,15,19],{"key":12,"text":13,"correct":14},"A","人工",false,{"key":16,"text":17,"correct":18},"B","机械",true,{"key":20,"text":21,"correct":14},"C","爆破","拆除建筑物时，应按自上而下对称顺序进行，先拆除非承重结构，再拆除承重的部分。不得数层同时拆除。当拆除一部分时，另与之相关联的其他部位应采取临时加固稳定措施，防止发生坍塌。承重结构件要等待所承担的全部结构和荷重拆除后再进行拆除。",{"id":6,"name":24,"category":25,"favorite":7},"高处安装、维护、拆除","特种作业"]