[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-720924":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":22},720924,401,1,"单选题","大型静置设备、设施拆除工程开工前,应根据工程特点、设备、设施情况、工程量等编制安全专项方案,应经技术负责人或监理工程师签字批准后实施。施工过程中,如需变更,应经()审批后实施。",[11,15,19],{"key":12,"text":13,"correct":14},"A","项目总工",false,{"key":16,"text":17,"correct":18},"B","原审批人",true,{"key":20,"text":21,"correct":14},"C","项目经理","大型静置设备、设施拆除工程开工前,应根据工程特点、设备、设施情况、工程量等编制安全专项方案,应经技术负责人或监理工程师签字批准后实施。施工过程中,如需变更,应经原审批人审批后实施。",{"id":6,"name":24,"category":25,"favorite":7},"高处安装、维护、拆除","特种作业"]