[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-720884":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":22},720884,401,1,"单选题","吊物在起吊离地()m时检查索具,确定安全后方可起吊,并严禁起重机超负荷作业。",[11,15,19],{"key":12,"text":13,"correct":14},"A","0.3",true,{"key":16,"text":17,"correct":18},"B","0.4",false,{"key":20,"text":21,"correct":18},"C","0.5","根据《建筑起重吊装工程安全技术规程》JGJ276-2012，吊物在起吊离地0.3m时检查索具，确定安全后方可起吊。",{"id":6,"name":24,"category":25,"favorite":7},"高处安装、维护、拆除","特种作业"]