[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-720881":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":22},720881,401,1,"单选题","高塔施工应及时与()取得联系,掌握气象情况。",[11,15,19],{"key":12,"text":13,"correct":14},"A","政府",false,{"key":16,"text":17,"correct":18},"B","气象部门",true,{"key":20,"text":21,"correct":14},"C","电视台","遇到雷雨、大风等恶劣天气时，应立即停止施工，严禁施工人员在铁塔、树木、电力线、电气设备等附近避雨、避风和逗留。铁塔组立时，应及时可靠地连接接地线，高塔施工应及时与气象部门取得联系，掌握气象情况。",{"id":6,"name":24,"category":25,"favorite":7},"高处安装、维护、拆除","特种作业"]