[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-720784":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":22},720784,401,1,"单选题","()内立管安装时其卡件宜设置型钢卡架。",[11,15,19],{"key":12,"text":13,"correct":14},"A","竖井内",true,{"key":16,"text":17,"correct":18},"B","桥架内",false,{"key":20,"text":21,"correct":18},"C","楼层内","1.立管明装，每层每趟立管从上至下统一吊线安装卡件，高度一致；竖并内立管安装时其卡件宜设置型钢卡架，将预制好的立管按编号分层排开，顺序安装，对好调直时的印记。校核预留甩口的高度、方向是否正确。支管甩口均加好临时丝堵。立管阀门安装朝向应便于操作和修理。安装完后用线坠吊直找正，配合土建堵好楼板洞。 2.立管暗装，安装在塘内的立管应在结构施工中预留管槽。立管安装后吊直找正，校核预留甩口的高度、方向是否正确。确认无误后进行防腐处理并用卡件固定牢固。支管的甩口应明露并加好临时丝堵。管进安装完毕应及时进行水压试验，试压合格后进行隐蔽工程检查，通过隐蔽工程验收后应配合土建填堵管槽。",{"id":6,"name":24,"category":25,"favorite":7},"高处安装、维护、拆除","特种作业"]