[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-720754":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":22},720754,401,1,"单选题","对只进行部分拆除的建筑,必须()。",[11,15,19],{"key":12,"text":13,"correct":14},"A","先将保留部分加固,再进行分离拆除。",true,{"key":16,"text":17,"correct":18},"B","人工拆除",false,{"key":20,"text":21,"correct":18},"C","先将分离拆除,再进行保留部分加固。","当采用机械拆除时，应从上至下，逐层分段进行，应先拆除非承重结构，再拆除承重结构。拆除框架结构建筑，必须按楼板、次梁、主梁、柱子的顺序进行施工，对只进行部分拆除的建筑，必须先将保留部分加固，再进行分离拆除。",{"id":6,"name":24,"category":25,"favorite":7},"高处安装、维护、拆除","特种作业"]