[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-720713":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":22},720713,401,1,"单选题","高处作业前,应由项目分管负责人组织有关部门对()设施进行验收,经验收合格签字后,方可作业。",[11,15,19],{"key":12,"text":13,"correct":14},"A","安全防雷",false,{"key":16,"text":17,"correct":18},"B","安全防护",true,{"key":20,"text":21,"correct":14},"C","临时","高处作业前，应由项目分管负责人组织有关部门对安全防护设施进行验收，经验收合格签字后，方可作业。安全防护设施应做到定型化、工具化，防护栏杆以黄黑（或红白）相间的条纹标示，盖件等以黄（或红）色标示。需要临时拆除或变动安全设施的，应经项目分管负责人审批签字，并组织有关部门验收，经验收合格签字后，方可实施。",{"id":6,"name":24,"category":25,"favorite":7},"高处安装、维护、拆除","特种作业"]