[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-720348":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},720348,398,3,"判断题","装修用钢管脚手架的立杆接长时可以使用搭接。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"只能对接，立杆上的对接扣件应交错布置：两根相邻立杆的接头不应设置在同步内，同步内隔一根立杆的两个相隔接头在高度方向错开的距离不宜小于500mm；各接头中心至主节点的距离不宜大于步距的1\u002F3；若搭接搭接长度不应小于1m，应采用不少于2个旋转和扣件固定，端部扣件盖板的边缘至杆端距离不应小于100mm。",{"id":6,"name":21,"category":22,"favorite":23},"登高架设","特种作业",0]