[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-720334":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},720334,398,3,"判断题","模板支撑架拆除时,第一步应先拆底部的扫地杆,再拆连墙件。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"后支的先拆，先支的后拆；先拆除非承重部分，后拆除承重部分，并做到不损伤构件或模板。扫地杆后拆。",{"id":6,"name":21,"category":22,"favorite":23},"登高架设","特种作业",0]