[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-720038":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":22},720038,398,1,"单选题","实行施工总承包工程的脚手架专项施工方案应由施工企业()部门的专业技术人员编制。",[11,15,19],{"key":12,"text":13,"correct":14},"A","工程",false,{"key":16,"text":17,"correct":18},"B","技术",true,{"key":20,"text":21,"correct":14},"C","安全","",{"id":6,"name":24,"category":25,"favorite":26},"登高架设","特种作业",0]