[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-719971":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":22},719971,398,1,"单选题","工作结束前不能形成稳定架构的部分应采取临时()措施加固。",[11,15,19],{"key":12,"text":13,"correct":14},"A","拉撑",true,{"key":16,"text":17,"correct":18},"B","隔离",false,{"key":20,"text":21,"correct":18},"C","支顶","",{"id":6,"name":24,"category":25,"favorite":26},"登高架设","特种作业",0]